Project Management Professional - QP1-Part3

13. Any numbering system that is used to monitor project costs by category such as labor, supplies, or materials, for example, is called 
a. Chart of accounts
b. Work breakdown structure
c. Universal accounting standard
d. Standard accounting practices
14. A person who is involved in or may be affected by the activities or anyone who has something to gain or lose by the activity of the project is called a:
a. Team member
b. Customer
c. Stakeholder
d. Supporter
The following should be used for questions 15 through 17.
A project manager is assigned to a project early in the project lifecycle. One of the things that must be done is to do a justification for the project. Since very little information is known about the project, the estimates are considered to be rough estimates. The following table is the project manager’s estimate of the cash flow that will take place over the next five years.
End of Year Cash Flow In Cash Flow Out
1                        0                  500,000
2                   300,000              90,000
3                    400,000            100,000
4                    100,000             175,000
5                      50,000              35,000
15. What is the payback period for this project?
a. One year
b. Two years
c. Three years
d. Four years
16. What is the net cash flow at the end of five years?
a. $50,000
b. - $50,000
c. $850,000
d. $100,000
17. If the net present value for each of the cash flows were calculated at a 10% interest rate, the net present value cash flow at the end of five years would be:
a. Greater than the total cash flow without the net present value applied
b. Less than the total cash flow without the net present value applied
c. The same as the total cash flow without the net present value applied
d. Unable to be calculated with the information supplied

18. A group of related projects that are managed in a coordinated way that usually include an element of ongoing activity is called a:
a. Major project
b. Project office
c. Program
d. Group of projects

19. During the full life cycle of the project, a plot of the project’s expected expenditure will usually follow a characteristic “S” shape. This indicates that:
a. There is a cyclic nature to all projects
b. Problems will always occur in the execution phase
c. There are high expenditure during closeout
d. The bulk of the project budget will be spent in the execution phase

20. A temporary endeavor undertaken to create a new product or service is called a:


a. New product development
b. Project
c. Program
d. Enterprise

<< Back to PMP-QP1-PART2  NEXT to PMP-QP1-PART4 >>    PMP-QP1-ANSWERS

Project Managment Professional PMP-QP1-ANSWERS

Project Managment Professional PMP-Question Pool 1-ANSWERS

Project Management Professional - QP1-Part2

6. You are the project manager for a large project. Some members of the project team have come to you and asked that they be permitted to work on a flexible schedule. Some of the other team members feel that it is important that all team members be on site at all times unless they are absent for business reasons. What should you do?
a. Turn down the request for flexible time schedules
b. Accept the request for flexible time schedules
c. Arrange a meeting of the project team members and allow them to decide
d. Discuss this problem with your manager and act on the results of the meeting

7. You are the project manager for a project that has high visibility. Your manager wants you to prepare a presentation for him to present at a conference. Most of the material in the presentation will be facts that are the results of your project. Your manager intends to present the material under his own name. Your name will not appear. What should you do?
a. Refuse to work on the presentation unless you are listed as a coauthor
b. Do the work as you were told by your manager
c. Present your own presentation
d. Meet with your manager’s manager and discuss the problem
8. You are managing a project and the customer’s engineer visits your facility on an inspection and general getting acquainted tour. During the tour they make the comment that the parts that are being designed should be in stainless steel instead of plain steel with enamel. What should you do?
a. Authorize the change in design to your engineers
b. Continue with the present design
c. Speak to the visiting engineers and discuss having an informal meeting between
your engineers and the visiting engineers
d. Ask the visiting engineers to submit a change proposal to the change system

9. Which of the following is the example of a conflict of interest?
a. You are the fourth cousin of a vendor supplying parts to a project in your company
b. You are the owner of a company that is supplying parts to a project that you are managing
c. You receive a gift from a supplier of parts for your project
d. A supplier tells you sensitive information, in confidence, that allows you to select another supplier for your project

10. You are the project manager for a large project that is completed on time and on budget. The customer and all of the stakeholders are pleased with the results. As a direct result of the successful completion of the project, your manager approves a bonus of $25,000 for you. There are fifteen members of the project team. One of the people in the project
team has been a very low contributor to the project; the other fourteen have all been above standard. What should you do with the money?
a. Keep the money yourself; you deserve it. And the manager gave it to you
b. Divide the money equally among all the team members
c. Ask the team members how they would divide the money
d. Divide the money equally among the team members except for the substandard
team member

11. One of the members of your project team comes to you and says that he heard that one of the suppliers to the project had given a substantial gift to one of the project team members in hopes that the team member would favor his company with a purchase order. The company was favored with a purchase order for the parts. What should you do?
a. Talk to the person and get him or her to give back the gift
b. Investigate the matter completely
c. Cancel the purchase order with the supplier
d. Meet with your manager and discuss the problem
12. Decomposing the major deliverables into smaller, more manageable components to provide better control is called:
a. Scope planning
b. Scope definition
c. Scope baselining
d. Scope verification

Project Management Professional - QP1-Part1

1. You are a project manager working on a project to market a new product. The deliverables of the project have been established, and the project work has begun. A contract to deliver the deliverables has been signed. The customer who has signed the contract has telephoned you to request additional work to be done on the project. This work will affect the budget but not the schedule of the project. This project has a high priority with your company. What should you so next?
a. Do what the customer asks you to do and add the additional requirements to the original contract   
b. Refuse the request and send a memo to your management explaining the situation
c. Respond to the customer’s request by explaining the change procedure and askingthat he or she submit a request for change
d. Arrange to meet with the project team to discuss this change

2. You are the project manager for a high visibility project. The margin on this project is low,and it is extremely important that the cost estimates for the work on the project be accurate. While reviewing the cost estimates for this project you notice that one of the cost estimates for an element in the WBS is 10% higher than two previous projects for very similar work. What should you do?
a. Accept the estimate because you trust all of the people on your project team, and they are responsible for estimates
b. Reduce the estimate and add the additional budget to the management reserve
c. Ask the person responsible for the estimate to explain the difference and bring supporting information to you
d. Reduce the estimate and add the additional budget to the contingency reserve

3. You are managing a project in a foreign country. In this country there is a normalpractice for business people to exchange gifts when very large contracts, such as the one you are working on, are signed. The gift is of a greater value than your company’s policy for gift exchange will allow. You have given a gift of similar value to the customer’srepresentative already. What should you do?
a. Take the gift
b. Contact your company’s management and seek for assistance
c. Refuse the gift graciously, explaining your company’s policy
d. Ask the customer’s representative to give the gift to your manager.

4. You are the manager of a research group that is developing a new chemical material.You hire a person from a competing company who has a great deal of expertise in thisarea. The person contributes greatly to the progress of your project. Duringconversation with the person you determine that many of this person’s ideas weredeveloped by the competing company. What do you do?
a. Tell the person that he or she should not mention that the ideas came from another company
b. Sign a nondisclosure agreement with this person before he or she leaves your company
c. Accept the new ideas
d. Investigate the employee for security reasons

5. You are managing a project that is in process. A large and unexpected problem occurs that will cause a delay in the schedule in excess of the contingency schedule for the project. What should you do?
a. Look at other tasks in the schedule and see which ones should be reduced to allow time for this problem to be worked
b. Reduce testing on the completed tasks
c. Require mandatory overtime for the project team
d. Speak to the stakeholders about getting additional time and budget for the project

Go  to PMP-QP1-Part2

<< Back to PMP-QP1-PART1  NEXT to PMP-QP1-PART2 >>    PMP-QP1-ANSWERS

VCP-511 VMWare

QUESTION 1
Which three modules are optional components that can be added from the vCenter Server installer? (Choose
three.)
A. VMware vCenter ESXi Dump Collector
B. VMware vCenter Storage Monitoring
C. VMware vSphere Web Client
D. VMware vCenter Orchestrator
E. VMware vSphere Update Manager
Correct Answer: ACE
Section: (none)
Explanation
Explanation/Reference:
Explanation:
Page 200 from vsphere-esxi-vcenter-server-50-installation-setup-guide.pdf
QUESTION 2
What do changes made to resources available in a parent pool affect in a resource pool hierarchy?
A. Child pools
B. Sibling pools
C. Sibling and child pools
D. Root resource pools
Correct Answer: C
Section: (none)
Explanation
Explanation/Reference:
Explanation:
A resource pool can contain child resource pools, virtual machines, or both. You can create a hierarchy of
shared resources. The resource pools at a higher level are called parent resource pools. Resource pools and
virtual machines that are at the same level are called siblings. The cluster itself represents the root resource
pool. If you do not create child resource pools, only the root resource pools exist.
QUESTION 3
What are two benefits of virtual compatibility mode for RDMs, as compared to physical compatibility mode?
(Choose two)
A. Allows the use of SAN-aware applications
B. Allows for cloning
C. Allows for the use of array-based snapshots
D. Allows for template creation of the related virtual machine
Correct Answer: BD
Section: (none)
Explanation
Explanation/Reference:
Explanation:
Page 39 from vsphere-esxi-vcenter-server-50-virtual-machine-admin-guide.pdf
QUESTION 4
An existing vSphere environment will be upgraded to vSphere 5. The current implementation utilizes ESX 4.1
and the new implementations will ESXi 5.x.
In which two ways will the new ESXi 5.x implementation differ from ESX 4.1 implementation? (Choose two)
A. VMware ESXi 5.x does not provide a host-based firewall.
B. VMware ESXi 5.x can boot from additional sources, such as a USB drive.
C. VMware ESXi 5.x does not provide local command-line management capabilities.
D. VMware ESXi 5.x can support virtual machine which larger resource configurations.
Correct Answer: BD
Section: (none)
Explanation
Explanation/Reference:
Explanation:
Option A is incorrect, ESXi have a internal firewall.
Option B is correct.
Page 28 from vsphere-esxi-vcenter-server-50-installation-setup-guide.pdf Option C is incorrect, ESXi have local
command-line but is necessary enable it.
Page 9 from vsphere-esxi-vcenter-server-50-command-line-interface-getting-started-guide.pdf
Option D is correct. See all Maximum configuration for ESX 4 and ESX5 document.
Some example:
ESX 4
Max CPU - 8
ESX 5
Max CPU - 32
QUESTION 5
Click the exhibit button.
Based on the exhibit, what is the reason that none of the paths are marked as preferred?
A. A preferred path has been selected, but the Refresh button must be pressed to reflect the change.
B. A preferred path cannot be selected.
C. A preferred path has not been chosen.
D. A preferred path has not been chosen because insufficient Active paths exist
Correct Answer: B
Section: (none)
Explanation
Explanation/Reference:
Explanation:
QUESTION 6
Which resource management technique can be used to relieve a network bottleneck by a virtual machine with
occasional high outbound network activity?
A. Apply traffic shaping to the port group that contains the virtual machine.
B. Convert traffic shaping from a nNetwork Standard Switch to a vNetwork Distributed Switch.
C. Apply traffic to the other virtual machines in the same port group.
D. Apply traffic to the virtual machine with high activity.
Correct Answer: A
Section: (none)
Explanation
Explanation/Reference:
Explanation:
Page 54 from vsphere-esxi-vcenter-server-50-networking-guide.pdf
QUESTION 7
VMware vCenter Site Recovery Manager requires which two VMware products as part of the solution?
A. vSphere HA
B. VMware ESXi
C. VMware vCenter Server
D. VMware Data Recovery
Correct Answer: BC
Section: (none)
Explanation
Explanation/Reference:
Explanation:
Option A is incorrect:
vSphere HA is used to perform High Availability in local environments, and is not needed in vCenter Site
Recovery Manager environment.
Option B is correct:
ESXi run virtual machines of virtual environment.
Option C is correct:
VMware vCenter Server help to manage Site Recovery Manager actions.
Option D is incorrect:
VMware Data Recovery is used to perform backup of virtual machines.
QUESTION 8
Which tool defines the Image Profiles used with Auto Deploy?
A. The vSphere Client via the Image Profiles management plug-in
B. The vSphere Power CLI image builder cmdlet
C. The vSphere CLI esxcfg-image utility
D. The vSphere CLI esxcli image add command
Correct Answer: B
Section: (none)
Explanation
Explanation/Reference:
Explanation:
http://pubs.vmware.com/vsphere-
50/index.jsp?topic=/com.vmware.vsphere.vcenterhost.doc_50/GUID-3B5AF2B1-C534-4426- B97AD14019A8010F.
html
QUESTION 9
Under which two situations does the dead space reclamation feature VAAI Thin Provisioning offer the ability to
reclaim blocks of a thin provisional LUN on a array? (Choose two)
A. When a virtual machine is migrated to a different datastore.
B. When a guest OS files in a virtual disk are deleted.
C. When a virtual machine is migrated to a different host.
D. When a virtual disk is deleted.
Correct Answer: AD
Section: (none)
Explanation
Explanation/Reference:
Explanation:
Page 188 from vsphere-esxi-vcenter-server-50-storage-guide.pdf
QUESTION 10
An administrator receives a complaint that a virtual machine is performing poorly. The user attributes the issue
to poor storage performance.
IF the storage array is the bottleneck, which two counters would be higher than normal?
(Choose two)
A. Average device latency per command, in milliseconds (DAVG per cmd)
B. Average ESXi VMKernel latency per command, in milliseconds (KAVG per cmd)
C. Average virtual machine operating system latency per command, in milliseconds (GAVG per cmd)
D. Number of SCSI reservation conflicts per second (CONS per second)
Correct Answer: AD
Section: (none)

Explanation

An administrator has purchased a new 10GB Converged Network Adapter (CNA) for installation in system that is running ESXi 5.x. the administrator has downloaded the latest driver from the hardware vendor and wants to include the driver in an image. The image profile acceptance level is set to VMwareAccepted and the driver acceptance level is set to Partner Supported.

A.driver will be included, but the support diverted to vendor
B.image will be created but driver will not be included
C.image can not be created
D.driver will include, and support will be provided by VMware.


Explanation:
The acceptance level of all VIBs on a host must be at least as high as the host acceptance level. For example, if the host acceptance level is VMwareAccepted, you can install VIBs with acceptance levels of VMwareCertified and VMwareAccepted, but you cannot install VIBs with acceptance levels of PartnerSupported or CommunitySupported. To install a VIB with a less restrictive acceptance level than that of the host, you can change the acceptance level of the host by using the vSphere Client or by running esxcli software acceptancecommands.

Setting host acceptance levels is a best practice that allows you to specify which VIBs can be installed on a host and used with an image profile, and the level of support you can expect for a VIB. For example, a
CommunitySupported VIB might not be recommended for an ESXi server in a production environment.
http://pubs.vmware.com/vsphere-50/topic/com.vmware.vsphere.upgrade.doc_50/GUID- 27BBBAB8-01EA-4238-8140-1C3C3EFC0AA6.html